Pages

Friday 22 May 2015

Alfresco and Garage roofing


Frames for alfresco and garage mostly up. Really like the alfresco. All ready for our outdoor bar fridge and kitchen.





 The alfresco view from inside the house. They installed the ceiling and tiles on the same morning. I was planning to put in some insulation. Probably do it through the man hole later. 




The garage still waiting to be roofed.


Friday 15 May 2015

Scaffolds down

Just finished painting the eaves. Plumber will be coming next week to fix a few issues. Wall and roof insulation mostly done. Will have to do Alfresco roof myself as it was not mentioned in the contract. Also waiting for electrician to pull through a few missed external points. 


Tuesday 12 May 2015

Render and eaves

Just finished bricking. They are putting in the eaves. Front of house already rendered. Still waiting for brick cleaner to come.